Percent complete
Specifies what percentage of the estimated durations specified by the steps in the
predicted workflow for the job are completed.
RICOH ProcessDirector calculates this percentage by dividing the sum of the estimated durations of the processed steps in the current workflow by the sum of the estimated durations specified for all the steps in the predicted path of the job.
You can see this value by hovering over the blue bar on the bottom of the View job in workflow window.
- Database name
- Job.DT.PercentComplete
Usage notes:
- If a job has the Included in estimated duration value set to No, RICOH ProcessDirector ignores that step when calculating the Percent complete property.
- If the estimated duration of any of the steps in the predicted path change, the Percent complete property uses the new values.
- If the job is processed again, goes back to a previous step in its workflow, or changes workflows, RICOH ProcessDirector calculates the Percent complete again.
- If the workflow is edited while the job is being processed, the Percent complete property is reset to 0%. You must process the job again if you want to track the Percent complete of the job.